Aruba Airport Authority N.V. logo

Aruba Airport Authority N.V.

  • PAX: 1,902,067
  • IATA: AUA
  • ICAO: TNCA

Aruba Airport's next project - West Apron Extention

3 new parking positions to be added

After completing the first phase of the West Apron extension which included 2 new parking stands (16 and 17) created especially for type C aircraft, AAA recently started the second phase of the extension project which includes parts A and B.


In the second phase, a further extension will be completed adding Gates 13, 14 and 15. Additionally, an extension of taxiway Kilo will be carried out connecting to the apron taxiway.
2 New apron flood lights will also be installed, as well as new drain slots to collect water and oil that goes into a separation tank and afterwards into the storm water ditch.
The West Apron extension is set to be completed by the end of December 2018.