Gateway 2030: Utility Building Switch-over

During the month of February 2020 the switch-over of our chiller plant, airfield lighting system, navigations system and electricity and back up power continued and were concluded by the end of the month. Since then the current Terminal is connected to the new utility building.  The new guard house and main gate is scheduled to be handed over by the end of March 2020. This means that the enabling works would be successfully completed and the next phase to expand the terminal can commence.